Uniper’s portfolio combines large-scale power generation and management of energy supply chains. Uniper’s former parent company was E.ON, who now focus on the new energy world.
Uniper Power Station in Enfield had fire, suppression and voice alarm systems that had reached the end of their serviceable life. They needed modern control equipment which would combine controls for different extinguishing systems into a centralised control station. The extinguishing systems themselves also needed replacing or updating.
Senseco were chosen to provide a bespoke solution providing controls and upgrades for gas extinguishing, water mist and deluge systems along with a replacement voice alarm rack. Our power station expertise and ability to provide flexible, custom built solutions to meet Uniper’s needs were key to the project.
THE CHALLENGE
Uniper had separate operating systems for gas extinguishing, water mist and deluge systems all of which had become obsolete with parts no spare longer available. They needed consistency of operation for the different systems in a central location in their control room.
Cylinders and components needed replacing on gas extinguishing, water mist and deluge systems. The voice alarm system also needed replacing as it was at the end of it’s working life. Uniper needed to utilise a company with a wide experience of the different types of mechanical systems along with electrical controls.
The power station needed to remain operational with limited windows to carry out works in planned shut down periods. Therefore effective planning and coordination were vital to the success of the project.
Latest Case Studies
VIEW ALL >>>Work For Us
We are constantly recruiting as we grow, looking for engineers, customer service advisers, and many other roles, we offer attractive training opportunities and company benefits.
We also support apprenticeship schemes, and regularly employ and train young, hardworking individuals to join our team and embark on a rewarding career with a forward-thinking employer.